This addition and renovation project consisted of a 200 student, 14,000
square foot addition, which included classrooms, a guidance center and administration area additions. The three phased project also included a 20,000 square foot renovation throughout the existing
school. Phase I included
the classroom additions, administration and guidance additions,
athletic office renovations, and the HVAC upgrades; all Phase
I work was performed simultaneously. Phase II and Phase III
consisted of renovations to existing classrooms, the fit-out
of a new computer lab area, and cosmetic and aesthetic adjustments
to the main entrance of the school. The new storm
water management system and a new
sprinkler system were added while the school was occupied. |