| Overview: |
This addition and renovation project consisted of a 14,000
square foot, 200 student addition, which included classroom
additions, guidance center and administration area additions,
and a 20,000 square foot renovation throughout the existing
school. The project was a three phase project. Phase I included
the classroom additions, administration and guidance additions,
athletic office renovations, and the HVAC upgrades. All Phase
I work was performed simultaneously. Phase II and Phase III
consisted of renovations to existing classrooms, the fit-out
of a new computer lab area, and cosmetic and aesthetic adjustments
to the main entrance of the school. There was a new storm
water management system added and the installation of a new
sprinkler system while the school was occupied.
|